Creating environments where older adults thrive, from independent living apartments to specialised memory care households. Our factory-built approach ensures every detail of accessibility, infection control, and acoustic comfort is precision-engineered before a single module reaches the site.
Senior living facilities must balance hospitality-grade comfort with clinical-grade safety. All while controlling costs in a sector where margins are tight and regulatory scrutiny is intense.
Phased developments adjacent to occupied buildings create unacceptable risk profiles. Construction noise, dust, and contractor movement compromise resident wellbeing and infection control protocols.
Every element, door widths, turning circles, threshold details, grab rail backing, tap forces, must meet BS 8300 and Part M. Site-built variations from specification create compliance risk that is expensive to rectify.
Senior living demands sophisticated mechanical and electrical systems: nurse call, wander management, access control, HEPA filtration, emergency power, and assistive technology, all of which create coordination challenges for traditional sequential trades.
Labour-intensive fit-out, wet rooms, wide corridors, enhanced acoustic separation, specialised MEP, drives per-square-metre costs well above standard residential. Fixed-price factory manufacturing eliminates on-site cost escalation.
Senior living environments are governed by healthcare building standards, accessibility regulations, and infection control protocols that demand precision execution.
| Standard | Requirement | MODURA Compliance |
|---|---|---|
| HBN 00-09 | Infection control in the built environment, surface finishes, ventilation strategy, water safety | Non-porous surfaces with welded joints; HTM 04-01 compliant water systems pre-installed and pressure-tested |
| BS 8300 | Design of accessible and inclusive environments, full accessibility for physical, sensory, and cognitive needs | All modules designed to BS 8300-2:2018; accessibility audit conducted at factory before delivery |
| Door Widths | Clear opening width ≥ 926mm for all habitable rooms; wheelchair turning circle 1,500mm in bedrooms and bathrooms | Standard module door sets factory-installed with verified clear widths; turning circles modelled in BIM |
| Wet Room Design | Level-access showering with slip resistance R11 minimum; Altro or equivalent safety flooring with coved skirting | Factory-formed wet room floor cassettes with integrated drainage falls; slip resistance tested to BS 7976-2 |
| Nurse Call & Wander Management | Nurse call points at bedhead, en-suite, and day spaces; wander management detection at exits with staff alert integration | Pre-cabled containment routes with pull-through draw wires; system agnostic, compatible with all major manufacturers |
| Acoustic Performance | DnT,w+Ctr ≥ 50dB between bedrooms; reverberation time ≤ 0.6s in communal spaces (HTM 08-01) | Independent module structure with acoustic break between units; factory-tested and certified |
| Fire Safety | 120-minute structural fire resistance; L1 fire detection and alarm system; sprinklers to BS 9251 | Full 120-minute compartmentation with intumescent perimeter seals at module joints; concealed sprinkler pipework |
| Air Quality | HEPA filtration to ISO 16890 ePM1 80%; minimum 10 l/s per person fresh air; positive pressure in clinical zones | Dedicated ventilation module per floor plate; filter change indicators accessible from corridor for maintenance without entering rooms |
| Emergency Power | Life safety systems on UPS with minimum 3-hour autonomy; generator connection for extended outages | Pre-wired essential circuits with automatic transfer switch; central battery system tested at factory |
Our manufacturing approach guarantees that every accessibility detail, every acoustic separation, and every infection control measure is executed to specification, not left to the variability of on-site workmanship. Modules arrive with wet rooms fully tiled and tested, MEP systems commissioned, and finishes inspected under factory quality control.
Our modular system scales across the full continuum of care, from active adult communities to high-acuity nursing environments.
Self-contained 1 and 2-bedroom apartments for active seniors. Open-plan layouts with adaptable kitchens, level-access showers, and private outdoor terraces. Community hub modules provide lounges, libraries, and fitness spaces.
Studio and 1-bedroom suites with 24-hour care capability. Each suite includes a fully accessible en-suite wet room, kitchenette, and integrated nurse call. Staff base modules with medications room, sluice, and equipment store serve each cluster of 8–12 suites.
Small-scale households of 10–14 residents with domestic-scale kitchen, dining, and living spaces. Continuous loop corridor design eliminates dead ends; colour-coded wayfinding integrated into interior finishes; secure garden modules with raised planters and sensory planting.
Continuing Care Retirement Communities combining independent living, assisted living, memory care, and skilled nursing on a single campus. Modular construction enables phased delivery, open independent living first to generate revenue while care wings complete.
Senior living operators choose modular for single-level, barrier-free residential buildings delivered move-in ready. Our LGS design library includes single-storey villa formats (Harmony House) that adapt directly to senior-living floor plans, with accessible bathrooms and step-free entries engineered in from the start.
| Program | Delivery | Approach |
|---|---|---|
| Independent-living villas | LGS volumetric from standard design library | Single-level layouts, step-free entries |
| Assisted-living residences | Turnkey fit-out, accessible bathrooms | Grab-bar blocking and clearances factory-integrated |
| Campus communities | Phased volumetric delivery | Villas and residence blocks phased across the site |
Senior living is underwritten on cost per bed and on the month the first resident moves in. Those two numbers, not the headline build rate, are what the comparison below is built around.
| Cost Line | Volumetric Modular | Traditional On-Site Build | Why They Diverge |
|---|---|---|---|
| Building shell and fit-out per residential m² |
~US$2,200–3,200 for independent and assisted living suites; ~US$2,800–3,900 for memory care and skilled nursing | ~US$2,000–2,900 for independent/assisted; ~US$2,600–3,600 for memory care and nursing | The module carries a shell premium because it must remain dimensionally true after road transport and re-levelling. It earns that premium back on programme and on repeatability. |
| Cost per bed assisted living, 60-unit scheme |
~US$145,000–215,000 per unit all-in | ~US$135,000–205,000 per unit all-in | Repeatable en-suite modules and shared MEP risers reduce the per-unit variance that drives contingency on a traditional build. |
| On-site programme 60-unit assisted living scheme |
7–11 months site time | 18–26 months site time | Roughly 80–85% of the build completes in the factory while groundworks and services proceed in parallel, so the site phase collapses to connection and commissioning. |
| Revenue impact of the programme gap | 7–11 months earlier to first occupancy | , | At typical assisted living fees, every month of earlier occupancy is recurring revenue. This line usually overwhelms the shell cost premium in a development appraisal. |
| Carry and financing cost | Lower: land is held for a shorter build period | Higher: land, professional fees, and debt carried 12–18 months longer | At a 7.5% cost of capital on the construction draw, a shortened programme removes a material amount of interest from the development budget. |
| Phasing and expansion | Additional wings added without closing the operating building | Phased expansion disrupts residents and requires decanting | A CCRC built in phases of modules can keep occupied accommodation running while the next phase is installed, which protects occupancy during growth. |
| Accessibility and wet areas | Level thresholds, roll-in showers, and grab-rail blocking installed and inspected at the factory | Same standards; verification depends on site trades | Accessibility detail is the most commonly snagged item in later-living projects, and factory inspection catches it before the wall is finished. |
Months from contract signature for identical unit count and care provision, with a traditional on-site programme shown alongside for comparison.
| Milestone | Modular (month) | Traditional (month) | What Happens |
|---|---|---|---|
| Design freeze and care-model briefing | 0–2 | 0–4 | Unit mix, care levels, staffing zones, and dining and therapy provision agreed. Resident circulation separates resident routes from service routes. |
| Groundworks and slab | 2–4 | 4–7 | Foundations, drainage, and service entry. Modular tolerances are tighter here because modules arrive dimensionally complete. |
| Factory production | 3–7 (in parallel) | , | Steel frame, envelope, wet rooms, accessibility blocking, and finishes completed under factory overhead. |
| Module delivery and install | 7–8 | , | Modules craned and connected. En-suite pods arrive as finished wet rooms rather than site-built units. |
| Structure and weather-tight | 8 | 8–14 | Building is watertight within days of the first delivery, which removes the weather exposure that drives programme risk on site. |
| MEP connection and commissioning | 8–10 | 14–22 | Inter-module services joined and commissioned. Nurse-call, fire alarm, and access control integrated and tested. |
| Acoustic and accessibility verification | 10 | 22–24 | Party-wall sound separation and accessibility detailing verified. Both are high-frequency snag categories in later-living fit-out. |
| Handover and licensing | 10–11 | 24–26 | Snagging, operator fit-out, and licensing inspections. Fewer defects typically arise because the module was inspected in the factory. |
| First resident move-in | Month 11 | Month 26–28 | This is the line the appraisal turns on: 15 months of earlier fee income against a modest shell cost premium. |
Operators, lenders, and licensing authorities ask for evidence rather than assurance. These are the named certifications behind the MODURA structural and envelope system and what each covers in a care setting.
| Document | Issued By | What It Covers in a Care Build |
|---|---|---|
| ICC-ES ESR-5348 | ICC Evaluation Service | Structural evaluation of the modular frame and connection system, including the stacked configurations used for multi-storey assisted living and the bracing that keeps upper floors stable. |
| Intertek ISO 3008-1 fire test | Intertek | Fire resistance of compartment boundaries, the assemblies separating units, corridors, and escape routes in a building where many residents require assistance to evacuate. |
| SGS CPR EN 14350 | SGS | European conformity assessment for envelope and structural components, supporting CE-marking documentation for European operators and their licensing submissions. |
| Q355B steel material report | Mill certificate with third-party verification | Grade and mechanical properties of the structural steel actually used, the traceability document requested during factory audits and lender due diligence. |
| STC 55 / IIC 52 acoustic data | Laboratory test report | Airborne and impact sound performance between units. Noise transfer between neighbouring apartments is the most frequent complaint in later-living post-occupancy surveys. |
| ISO 9001 / ISO 14001 / ISO 45001 | Accredited certification bodies | Factory quality, environmental, and safety management systems, the evidence base for operator audit programmes and operator-led quality inspections. |
| Accessibility & fire strategy | Design-team specification to destination code | Level thresholds, turning radii, grab-rail blocking, and progressive-horizontal-escape strategy specified to the destination jurisdiction and verified at commissioning. |
Documentation pack on request. The full set, ICC-ES ESR-5348, the Intertek ISO 3008-1 fire test report, the SGS CPR EN 14350 certificate, the Q355B steel report, and the ISO management-system certificates, is available for operator due diligence, lender submissions, licensing reviews, and factory audits. Request the documentation pack →
These are the care typologies our network delivers most often, each linked to the detailed construction guide for that facility type.
En-suite assisted living suites with shared dining, therapy, and wellness provision, stacked to four storeys. See the assisted living construction guide.
Medicare-certified nursing accommodation with higher MEP density, medical gas provision, and therapy spaces. See the skilled nursing facilities guide.
Independent living apartments and senior housing communities where repeatable unit types reduce cost per bed. See the senior living facilities guide.
Community centres and adult day programmes with accessible circulation, daylight, and flexible activity rooms. See the senior centres and adult day care guide.
Single-bedroom hospice households with family space, private outdoor access, and a domestic rather than institutional character. See the hospice and palliative care guide.
Physical therapy and rehabilitation clinics with gym floors, treatment rooms, and high floor loadings. See the physical therapy and rehabilitation guide.
These five recur on nearly every care enquiry, whether the client is an operator, a healthcare REIT, or a developer building to an operator's specification.
Will a factory-built building feel institutional to residents?
It should not, and the design discipline that prevents it is the same one used in hospitality: deliberate ceiling heights, daylight on the main elevation, and finishes selected for a domestic rather than clinical character. What the factory changes is consistency, not character: every unit is built to the same tolerance because each one is built in the same jig. The approach is described in our senior living facilities guide.
Can upper floors be modular in a multi-storey care building?
Yes. Stacked configurations are covered under the ICC-ES ESR-5348 structural evaluation, with the load path and bracing designed for the stack rather than for a single storey. The practical limit is usually driven by crane access and by how many modules the site can receive per day, not by structural capability. Details are in our building systems overview.
How do you handle nurse call, medical gas, and care technology?
These are designed into the module rather than added afterwards, and they are tested in the factory where a fault can still be corrected without opening a finished wall. Nurse-call, access control, and fire alarm integration are commissioned on site once inter-module connections are made. Because the routing is fixed at design freeze, the care-technology specification needs to be settled early, the same discipline described in our project process.
What happens if the operator changes the unit mix after production starts?
It costs more than it would on site, and we say so up front. A change to unit types while modules are on a jig disrupts a sequence other modules are already queued behind. The answer is a disciplined design freeze with the operator and their clinical advisor involved before production, not during it. Changes are cheapest in month one and most expensive in month seven.
Can a phased CCRC be built without closing the occupied building?
Yes, and this is the strongest argument for modular in a continuing-care setting. Additional wings can be installed alongside an operating community, with site hours and delivery windows scheduled around residents, so the next phase does not require decanting anyone. Operators expanding an existing community typically plan in modules rather than in one large contract for exactly this reason.
Discuss your project with our later living specialists. We will prepare a feasibility assessment covering unit mix, care model integration, and phased delivery programme, at no cost.