A streamlined process that brings certainty to construction. Every project follows the same disciplined path, design, manufacture, assemble, deliver, managed by one integrated team from start to finish.
Our engineering team and licensed partners translate your project brief into a complete modular building design. We use BIM (Building Information Modeling) to plan every module, every connection, and every system before a single piece of steel is cut. This digital-first approach eliminates clashes, optimizes material usage, and ensures every module fits perfectly on site.
Modules are manufactured in partner factories with climate-controlled production halls using precision tooling and assembly-line processes. Each module passes through dedicated workstations: steel framing, electrical rough-in, plumbing, insulation, drywall, flooring, cabinetry, and final finishes. Quality inspections at every station, with digital checklists tracked in real time.
Modules are transported to site on flatbed trucks and lifted into position by crane. Our site team connects modules structurally, links MEP systems, and seals weatherproof joints. Because 80% of the work is already done in the factory, on-site assembly is fast, quiet, and minimally disruptive to surrounding properties.
Final commissioning of all building systems, quality punch-list resolution, and comprehensive inspection. We deliver complete documentation: including as-built drawings, warranty manuals, maintenance schedules, and certification records. Keys are handed over with a walk-through orientation for your facilities team.
Production runs through partner factories with documented quality management. Every workstation has digital checklists, tolerance gauges, and photographic documentation. Module dimensions are verified to ±2mm accuracy, a level of precision impossible to achieve on a traditional construction site exposed to weather, dust, and variable labor.
Modules are designed to ship on standard flatbed trucks, maximizing transport efficiency. We coordinate logistics routes, permits, and escort vehicles for oversized loads. On-site, modules are craned into position following a pre-planned sequence. A 100-module building can be fully assembled in under 3 weeks.
Most modular programmes that go wrong do not fail in the factory. They fail because a phase was released before its inputs were frozen. These are the gates we hold every project to, and the documents that close them.
| Gate | Must Be Complete | Who Signs Off | If It Slips |
|---|---|---|---|
| Gate 1, Release to engineering | Site survey, geotechnical report, code jurisdiction confirmed, unit mix frozen, brand or client standard received | Client PM + our design lead | Freeze date moves 1:1. No cushion is consumed because production has not started |
| Gate 2, Release to production | Permit issued (or approved for construction), structural calculations stamped, MEP coordination model clash-free, procurement of long-lead items released | Client PM + engineer of record | This is the only gate where slip is expensive, steel and fixtures are ordered against it |
| Gate 3, Release to transport | Factory inspection report per module signed, module serial list matched to erection sequence, crane plan approved, route permits issued | Factory QC + our logistics lead | Modules queue in the yard; yard storage is cheaper than standing site time |
| Gate 4, Release to handover | Module connections tested, MEP pressure and commissioning complete, punch list resolved, as-built set issued | Our site lead + client PM | Delay lands on occupancy, not on structural warranty |
The four gates are not equally priced. Gates 1, 3 and 4 cost time. Gate 2 costs money, because release to production commits steel procurement, fixture orders, and jig time against a fixed module list. A change made after Gate 2 is not a drawing revision. It is a factory change order, and it typically carries 4–9% of the affected module’s fabrication value plus a schedule restart on that line. This is why we push design decisions forward into Gate 1 rather than accepting “we’ll confirm finishes later.” The factory rewards early certainty and punishes late flexibility, the exact inverse of site construction.
Modular procurement does not map cleanly onto a conventional cost-plus or lump-sum site contract, because a large share of the value is delivered before anything arrives on site. The structure that works in practice:
The practical consequence for a lender is that modular draws are evidence-backed by factory inspection records rather than by a site quantity surveyor’s estimate. Our financing guide and lending guide cover what lenders ask for and how the draw cycle differs, and our RFP and procurement guide covers how to write a modular scope that vendors can actually price.
The ±2mm module tolerance quoted above is a production claim, and it is backed by named third-party evaluation rather than internal quality language:
Together these are what make a factory inspection report usable by a building official, a lender’s inspector, and an insurer. Our MBI certification and standards guide explains how these map onto the US code path, and the insurance and risk management guide covers why insurers price the factory inspection record favourably.
Our partner network runs six production bases in China with a permanent modular line added in 2025 for US permanent-occupancy projects, and has delivered to 60+ countries. The Soledad, California interim housing community (2026) is our most recent US delivery, a project that exercised the full code path a permanent US multifamily or hospitality build would need: US jurisdiction, California amendments, permanent-line production, and documented handover. Our single-family buyers guide and healthcare facilities guide show how the same process adapts across building types.