Volumetric Modular

80–95% Factory Complete. One Module, One Room, One Delivery.

Volumetric modular construction delivers fully enclosed 3D modules — complete with mechanical, electrical, plumbing, and interior finishes — fabricated under controlled factory conditions. Each module is a structural steel box that stacks and connects on site to form a finished building in weeks, not months.

How It Works

From Raw Steel to Finished Room

Each volumetric module follows a 14-station production line inside our factory. Every station has defined quality gates — nothing moves forward without passing inspection.

01

Steel Frame Fabrication

Structural steel frame welded to ±1mm dimensional tolerance. 550 MPa yield strength S355 steel. Base frame, columns, and roof beams assembled on precision jigs — full weld inspection at every joint before proceeding.

02

Enclosure & Weatherproofing

External wall panels, breathable membrane, sheathing board, and window apertures installed. The module is weather-tight before any internal work begins — no water ingress, no dew point risk, no construction moisture trapped inside the assembly.

03

MEP First Fix

All mechanical, electrical, and plumbing rough-in completed within the module. Conduits, pipework, duct runs, cable trays, and back boxes installed. Plumbing circuits pressure-tested to 10 bar. Electrical continuity verified circuit-by-circuit before enclosure.

04

Plasterboard & Insulation

Mineral wool insulation to external walls, floor, and ceiling achieving U=0.15 W/m²K. Fire-rated plasterboard to 120-minute standard. All joints taped and filled to Level 4 finish. Acoustic resilient bars at party wall locations. Airtightness <3 m³/h/m² at 50Pa verified by blower door test.

05

Finishes & Joinery

Floor coverings, ceramic wall tiles, and paint finishes applied under controlled humidity (40–60% RH) and temperature (18–22°C). Kitchen cabinetry, wardrobes, interior doors, skirtings, and architraves installed. All joinery fitted to ±1mm tolerance. No weather delays, no drying-out period.

06

MEP Second Fix & Commissioning

Sanitaryware, light fittings, switches, sockets, thermostats, and ventilation terminals installed. Full system commissioning: plumbing pressure hold test (30 min at 10 bar), electrical insulation resistance at 500V DC, HVAC airflow balancing, fire detection verification. Photographic record of every test result.

Technical Specifications

Volumetric Module Performance Data

Engineered to Eurocodes. Independently tested and third-party certified. Every value below is contractually guaranteed, not aspirational.

ParameterSpecificationStandard / Test Method
Structural FrameSteel S355, yield strength 550 MPaEN 1993-1-1 (Eurocode 3), EN 1090-2 EXC3
Dimensional Tolerance±2mm across any 3m faceBS 5606, laser-verified at Station 3 & Station 14
Maximum Module Size4.5m × 16.0m × 3.6m (W×L×H)Transport-limited; larger by special permit
Building Height CapabilityUp to 30 storeys (steel frame)EN 1993-1-8 joint design, concrete core for 12+
Fire Resistance120 minutes (integrity & insulation)BS EN 13501-2, Type IA/IB construction
Acoustic — AirborneDnT,w + Ctr ≥ 45 dBBS EN ISO 16283-1, tested in factory
Acoustic — ImpactL'nT,w ≤ 62 dBBS EN ISO 16283-2, tested in factory
Thermal TransmittanceU = 0.15 W/m²K (external wall)BS EN ISO 6946, 140mm mineral wool
Airtightness<3 m³/h/m² at 50 PaBS EN ISO 9972 (blower door, per module)
Design Life60 years (structural)BS 7543, BOPAS-accredited
Factory Completion80–95%Including MEP, finishes, joinery, appliances
Typical Programme12–20 weeks factory + 4–8 weeks siteSite = foundations, connections, commissioning
Why Volumetric

The Volumetric Advantage

When quality, speed, and predictability are non-negotiable, volumetric modular outperforms every other construction method. Here is why.

Maximum Factory Completion

80–95% of all work happens indoors, under controlled conditions. Trades work in sequence on a moving production line — no weather delays, no trade stacking, no rework from water damage. The result: zero-snag handover is the norm, not the exception.

Unmatched Repeatability

Every module is built to the same digital model on the same jigs by the same teams. Module #1 and module #200 are dimensionally identical within ±2mm. No site-to-site variance. No crew-to-crew variance. This repeatability compounds: stack tolerances remain predictable across 12+ storeys.

Parallel Programme

While modules are being fabricated in the factory, site teams pour foundations, install utilities, and prepare the podium. The moment the first module arrives, the building rises at 6–8 modules per day. A 100-unit apartment block can be weather-tight in under two weeks — cutting total programme duration by 30–50% versus traditional construction.

Tested Before Delivery

Every module undergoes factory acceptance testing (FAT) before leaving the production line: plumbing at 10 bar, electrical insulation at 500V DC, HVAC commissioning, fire system verification, blower door test. Defects found in the factory are fixed in minutes. Defects found on a traditional site take days and involve multiple trades.

Method Comparison

Volumetric vs Panelized vs Traditional

Choose the right system for your project. This comparison is based on a 100-unit, 8-storey apartment building.

MetricVolumetricPanelized (2D)Traditional
Factory Completion80–95%40–60%<5%
On-Site Labour (person-hours/m²)4–68–1218–25
Weather DependencyVery LowModerateHigh
Total Programme Duration16–28 weeks24–38 weeks52–78 weeks
Quality ConsistencyExcellentGoodVariable
Transport Cost (relative)HighLowN/A (materials only)
Design FlexibilityModerateHighVery High
Best ApplicationHotels, student housing, hospitals, multi-familyOffices, schools, low-rise residentialOne-off bespoke, very complex geometry
Capital Cost (relative to traditional)95–105%90–100%100% (baseline)
Whole-Life CostLower (quality, energy, maintenance)ComparableBaseline
0Max Factory Completion
0Dimensional Tolerance
0Fire Rating
0Design Life

Explore Volumetric for Your Project

Share your project brief and we will prepare a technical feasibility assessment with programme timeline, cost model, and module configuration options — typically within 72 hours.

Get a Quote