The financial risk on a modular project does not sit where most buyers expect it. It sits in the last ten percent. The modules arrive, the building is commissioned, the operator moves in, and somewhere between twelve and twenty-four months later the retention is released and the final account is agreed. That gap between occupancy and money changing hands is where the arguments live, and on a modular building it is longer and more complicated than on a site-built one, because the thing you are holding money against was mostly finished before it reached your land.
This article is about the closeout arithmetic: how retention is normally held, how the defects liability period interacts with the factory warranty, what a final account actually reconciles, and which clauses buyers should insist on before the first module goes into fabrication. It does not repeat the payment schedule mechanics, which our draw schedule guide covers from the lender's side, nor the warranty terms themselves, which the warranties and structural guarantees guide sets out in detail. What follows is the part in between: the money that stays on the table after the building is handed over.
What Retention Is Actually For, and Why It Works Differently on Modular
Retention is money the buyer keeps back from each payment as security against unfinished work and uncorrected defects. The standard construction arrangement holds somewhere around five percent of each interim payment, capped at a similar percentage of the contract sum, with half released at practical completion and the balance at the end of the defects liability period. Those percentages are contractual conventions, not fixed rules, and they vary by jurisdiction and by client. What matters is that the mechanism assumes a simple thing: that at practical completion, the building is substantially done and only a small tail of work remains.
On a modular project that assumption is only partly true. The modules were substantially complete in a factory under a quality system, and the factory QC process means a large share of the work was already inspected and closed out before shipping. What remains at practical completion is not the work itself but the interfaces: module-to-module joints, the site-made penetrations, the MEP tie-ins, the connections between the modular scope and whatever was built in situ. The retention is therefore being held against the highest-risk part of the project rather than against a random tail of finishing trades, which is a point in the buyer's favour, and it is the reason retention percentages negotiated for a site-built project should not simply be copied across.
There is a second difference that cuts the other way. Retention is calculated as a percentage of the contract sum, and a modular contract sum is unusually front-loaded, because fabrication consumes most of the cost in the first half of the programme. By the time practical completion arrives, the buyer has already paid for the majority of the value delivered, and the retention is the only meaningful leverage left. A buyer who accepts a small retention, or who releases it early to keep a supplier cooperative, gives up the only commercial instrument that survives into the defects period.
| Closeout instrument | What it protects | How it behaves on a site-built project | How it behaves on a modular project |
|---|---|---|---|
| Retention held from payments | Unfinished work and uncorrected defects | Held against a long tail of site trades still finishing | Held against interfaces that were never part of the factory scope |
| Performance bond | Supplier default before completion | Runs across a long construction period | Compressed window, mostly exposure during fabrication and shipping |
| Factory warranty | Defects in the modules as manufactured | Does not exist as a distinct instrument | Runs from module completion, which is months before practical completion |
| Defects liability period | The obligation to return and fix | Starts at practical completion, one calendar | Starts at practical completion but overlaps a warranty clock that started earlier |
| Final account | Reconciling what was actually owed | Reconciles variations against measured work | Reconciles variations against a largely fixed fabrication price plus site scope |
Read across that table and the structural problem becomes visible: the four instruments that protect a buyer start their clocks at different moments, and on a modular project the gap between them is wider. The factory warranty on a module may have begun eight or ten months before the building was handed over, because it starts when that module is complete, not when the building is complete. Unless the order says otherwise, a meaningful slice of the warranty has already been consumed by the time the operator gets the keys. The project timeline makes this obvious once you lay it out, and it is the single most negotiable point in a modular closeout.
The Two Clocks: Factory Warranty Versus Defects Liability Period
A defects liability period is the window during which the contractor must return and fix defects notified by the buyer, at no cost. A warranty is a separate promise about the condition of the thing supplied. In practice they overlap, and the overlap is where modular buyers lose money without noticing, because the same defect can be in-warranty under one instrument and out-of-warranty under the other.
The mechanism is straightforward. A defects liability period normally starts at practical completion of the whole building and runs for a stated number of months. A factory warranty on a module normally starts at the point that module is signed off in the factory. If modules were fabricated and held, or if the site programme ran long while modules sat in a yard, the two clocks diverge. A twelve-month factory warranty on modules completed in March, on a building handed over in December, leaves three months of warranty coverage at handover rather than twelve. The defects liability period may still cover the fix, but the supplier's own upstream warranty from its component manufacturers is likely to have expired, and that cost lands somewhere.
| Closeout element | Clock starts when | Typical stated length (confirm in your contract) | What buyers should do about it |
|---|---|---|---|
| Factory warranty on modules | When the module is completed and signed off in the factory | Varies by supplier and by assembly; commonly 12 to 24 months on the module as manufactured | Require the warranty clock to start at practical completion, or at delivery to site, not at factory sign-off |
| Defects liability period | Practical completion of the whole building | Commonly 12 months; 24 months is negotiated on some asset classes | Name the start event explicitly, because "completion" is ambiguous on a phased modular project |
| Structural warranty | Practical completion or first occupation, whichever the policy defines | Longer terms, typically 10 years or more, usually through a separate policy | Confirm the provider accepts an off-site manufactured system and has seen the evaluation report |
| Retention release | Half at practical completion, balance at end of the defects period | Contract-specific; commonly 50 percent at each milestone | Link the second release to a defined event, not to "agreement of the final account" |
| Final account agreement | After all variations, adjustments and set-offs are valued | Contract-specific; often stated as a period after completion | Put a long-stop date in the contract, or the account stays open indefinitely |
The negotiation is not difficult if it happens early. Ask for the warranty to commence at practical completion or at delivery, and accept that the supplier will want a limit. Where the supplier will not move the start date, the alternative is to shorten the period between factory completion and handover — which is a programme question, and a good reason to avoid fabricating modules months before the site can receive them. On a phased project, where modules for phase two are built while phase one is occupied, this becomes unavoidable, and the order needs a per-phase start date rather than a single project date.
There is a related trap for buyers who take early delivery of modules into storage. Once the modules are on your site or in your yard, the supplier's transit and storage obligations end, and the risk passes. If a module sits for four months before installation, the defects period may not have started and the warranty is running down. Our guide to Incoterms and imported modules deals with the transfer of risk at the port; the same logic applies at the site gate, and it should be written into the contract rather than assumed.
What the Defects Liability Period Obliges, and What It Does Not
The defects liability period is narrower than most buyers think, and it is worth being precise about the boundary before negotiating it. It obliges the contractor to return and remedy defects notified during the period. It does not oblige the contractor to improve the building, to correct a design the buyer approved, or to fix damage caused by the operator. And it does not cover everything that goes wrong: some failures are maintenance items that were always the owner's responsibility, and some are consequences of how the building was used.
On a modular project the boundary needs an extra line, because so much of the building was completed in a factory under a different legal entity and, often, a different contract. The party you contracted with for the modules may be the same party responsible for the site installation, or it may not. Where it is not, the defects liability period sits with one entity while the factory warranty sits with another, and the buyer ends up as the arbitration channel between them. That is a position worth refusing at tender stage.
| Failure type | Whose obligation during the defects period | Evidence needed to make the claim stick | Where it usually goes wrong |
|---|---|---|---|
| Module-to-module joint leak at the facade | Depends entirely on who was named for joint sealing in the order | Dated photographs, the joint register entry, and the sealant product record | Factory says the seal was complete at dispatch; installer says the module moved after landing; nobody has the mid-programme photographs |
| Service penetration seal failure | Whoever made the opening, which is often the buyer's own MEP contractor | Seal schedule with installer named per opening | The opening was made after handover, so it is not a construction defect at all |
| Condensation inside a module wall | Design responsibility, which may sit with the buyer if the specification was buyer-authored | Vapour barrier detail as built, plus the ventilation design assumptions | Diagnosed as a waterproofing defect when it is actually an air-tightness or ventilation failure |
| Door set failing to close or latch | Supplier, if the set was supplied complete as a tested assembly | The assembly certificate and the door schedule with the location | Closer was adjusted or replaced on site, which invalidates the assembly evidence |
| Uneven floor or out-of-tolerance junction | Split between foundation scope and module scope at the setting-out datum | The as-built setting-out survey and the tolerance stated in the order | No survey was taken at the right moment, so neither party can prove the other caused it |
| MEP tie-in leak or pressure loss | Whoever made the final connection | Pressure test record with the test date and the witness name | Test was done before secondary connections, so the passing record covers the wrong scope |
Two of those six rows are worth reading twice. The first is the joint leak, because it is the defect most likely to be expensive and least likely to be evidenced: the module leaves the factory sealed, the joint is made in the open, and unless somebody photographed the joint at the moment it was closed, the arguments run on assertion. The second is the floor tolerance, because it is the defect most likely to be blamed on the wrong party. Our site preparation scope guide sets out where the datum responsibility sits, and the defects period is where that scope split gets tested in practice.
Building the Defect Evidence Before You Need It
Almost every dispute at the end of a defects period is an evidence dispute, not a technical one. Both parties accept that the joint leaked. The question is who was responsible for the step that failed, and the answer depends on records made months earlier by people who have since left the project. A modular project makes this worse than usual because the evidence has to prove continuity across a boundary: factory records on one side, site records on the other, and the interface itself recorded by whoever happened to be there.
The practical response is to decide at tender what the evidence set will be, and to make each item a hold point rather than a promise. A hold point is a step that cannot be passed without the record being produced; the commissioning and handover guide covers the commissioning side of the same discipline. Four records do most of the work on a modular closeout.
- Module serial register with dates. Every module listed with its serial, its factory sign-off date, its dispatch date and its installed location. This is what converts a warranty argument from a discussion about the programme into a calculation.
- Joint closure record. Each module-to-module joint photographed after closure and before it becomes inaccessible, with the date, the product used and the person who did it. A joint under a closed ceiling with no photograph is, for practical purposes, unevidenced.
- Tolerance survey at installation. A setting-out and as-built survey taken while the modules are still accessible, referenced to the datum named in the order. Without it, a floor defect can be attributed to either side indefinitely.
- Pressure and flow test records with the correct scope. Tests performed after final connections, not before, signed by the party who made the connection. A passing test that covers the wrong scope is worse than no test.
None of this is expensive at the time. All of it is nearly impossible to reconstruct afterwards, because the people who were present are on another project and the cavities are closed. A buyer who asks for these four records at tender, and refuses to release the second half of retention until they are delivered as a complete set, has converted the defects period from an argument into an administrative process.
What the Final Account Actually Reconciles
The final account is the closing statement of what the project actually cost. On a traditional contract it is a measured reconciliation: the contract sum, plus variations, plus or minus provisional sums and prime cost items, less retention and any set-offs. On a modular contract the shape is different, and buyers who run it as though it were traditional tend to be surprised by where the movement comes from.
Because fabrication is largely fixed and finished early, the variation activity concentrates in two places: the site scope, where conditions differ from the assumptions, and the junction scope, where the modular package meets whatever was built in situ. The first is familiar. The second is the one to watch, because on a modular project the interfaces are frequently not clearly allocated at tender, and every variation that lands in an unallocated interface has to be valued by someone. Whoever values it first usually wins the argument about what it cost.
| Final account line | What moves it on a modular project | How to keep it from becoming a dispute |
|---|---|---|
| Contract sum for fabrication | Design changes after design freeze; anything altered once modules are on the line | Name the design freeze date in the contract and state that changes after it are variations at the supplier's rates, not absorbed |
| Site installation scope | Ground conditions, access constraints, crane standing arrangements, weather days | Fix the site survey as a buyer deliverable, so site-condition claims cannot be blamed on missing information |
| Interface and junction work | Allocation gaps between factory scope and site scope | Sign a junction register at contract stage naming the party and the rate for each interface |
| Preliminaries and supervision duration | Extensions of time, and the daily cost of site staff retained longer than planned | State the day rate for prolongation, and cap the total prolongation claim |
| Retention and set-offs | Defects not closed out at the release date; unfinished items recorded at completion | Define what counts as closed, and issue the completion snag list as a numbered schedule with owners and dates |
| Currency, duty and freight adjustments | Imported modules, exchange movement, and classification decisions at the border | Fix the basis of the landed price and name who carries duty differentials |
The single most valuable clause in that table is the junction register, and it is the one buyers most often leave out because it feels like a level of detail that can be settled later. It cannot. Once the junctions are built, every party has a reason to describe them as someone else's scope, and the final account becomes a negotiation about which of two plausible positions the buyer will accept. A register signed at contract stage, with a rate against each interface, converts that negotiation into an arithmetic exercise.
The same discipline applies to the completion snag list. On a modular building, the items recorded at practical completion are usually interface items rather than workmanship items, and they cluster at the junctions, the penetrations and the MEP tie-ins. Issuing that list as a numbered schedule with an owner and a date against each line does two things: it gives the retention release something concrete to be conditional on, and it prevents a defect raised in month eleven from being treated as new. Our quality comparison with site-built construction shows why the volume of snag items is typically lower on a modular project even when the value of each item is higher.
The Security Package: Retention, Bonds and What Happens If the Supplier Fails
Retention protects the buyer against defects. It does not protect against the supplier disappearing. Those are two different risks, and a modular project carries both in a compressed window: most of the money moves during fabrication, and most of the fabrication happens before there is anything on site to hold as security. A buyer who holds five percent retention against a supplier that fails at module twenty of sixty holds very little of value.
The instruments that cover supplier failure are a performance bond and, where the buyer is funding fabrication, an advance payment guarantee that reduces as modules are delivered. On a modular contract the important question is not whether a bond exists but what it is measured against. A bond valued on the contract sum assumes the supplier is delivering value evenly across the programme; a modular programme does not do that, because value is created in the factory and then transferred in a few weeks of lifting. A bond structure that steps down at delivery milestones reflects the actual risk better than one that steps down by calendar date.
The other protective step is entirely practical: delivery against payment. If payment for a module is conditional on that module being complete, inspected and ready to ship, the buyer's exposure to supplier failure is limited to the modules already paid for and not yet received, and the neatest way to keep that exposure small is to keep the payment schedule close behind the dispatch schedule. The surety bond guide covers how sureties assess a modular manufacturer, and a supplier that can obtain bond capacity at reasonable cost is telling you something about how its own surety reads its factory throughput.
Retention protects you against a defect. A bond protects you against a disappearance. A modular contract needs both, and it needs the delivery schedule and the payment schedule to stay within one module of each other.
Questions We Are Asked Before Every Modular Closeout
Should we hold the same retention percentage as on a site-built project? Not automatically. The risk profile is different: less workmanship tail, more interface risk. A buyer is often better served by a smaller retention held longer, tied to a defined defects period end, than by a larger one released early. The percentage matters less than the release conditions.
Can we get the factory warranty to start at handover rather than at module completion? It is negotiable and should be raised at tender, not after the order is placed. Where the supplier will not move the start date, the effective response is to compress the interval between factory completion and handover, or to negotiate a warranty period long enough that the consumed months do not matter.
Who fixes a joint that leaks two years after handover? Whoever was named for joint sealing in the contract, and that naming is the whole argument. If the order says nothing, the buyer will usually end up paying for the first repair while the parties dispute the second. A junction register signed at contract stage is the cheapest insurance available.
What should hold back the second half of retention? A complete set of closeout records, not a promise that the records exist. Module serial register, joint closure photographs, tolerance survey, and pressure test records with the correct scope. Make the release conditional on delivery of the set, and the set will be delivered.
How long should the defects liability period be on a modular building? Long enough to cover a full heating and cooling cycle and a full wet season, because that is when envelope and condensation defects actually appear. Twelve months achieves that in most climates; a project handed over in spring may want eighteen to be safe. Two years is sometimes negotiated on asset classes where a closure would be disruptive.
What if the final account is never agreed? Then the retention sits with the buyer and the dispute sits with everyone. Put a long-stop date in the contract after which unagreed items go to the named dispute process, and keep the retention release tied to the defects period rather than to agreement of the account, so the two do not become hostage to each other.
| Clause to settle before fabrication | Why it matters later |
|---|---|
| Warranty start event (factory sign-off vs practical completion) | Determines how much of the warranty the operator actually receives |
| Junction register with a named party and rate per interface | Turns final-account interface disputes into arithmetic |
| Retention release conditions and the second-release trigger | Prevents retention being held hostage to an unagreed account |
| Defects liability period start event on a phased project | A single project-wide date leaves later phases under-covered |
| Closeout evidence set, listed by item, as a release condition | Converts the defects period from argument into administration |
| Long-stop date for final account agreement | Stops the account staying open indefinitely |
The thread running through all of it is that a modular project front-loads the work and back-loads the risk. The building is largely finished before the site work starts, which is the whole commercial case, and it means the money that decides whether the project was a success is committed early while the evidence that protects it is only tested late. Buyers who write the closeout clauses at tender — warranty start, junction register, release conditions, long-stop date — get a defects period that runs as an administrative process. Buyers who leave them to be settled at handover get a negotiation, held at the worst possible moment, with the operator already in the building.